Discover exactly where Smart Money is moving capital in real-time. By registering on our platform, you unlock the complete ExpertFX ecosystem: high-precision consensus algorithms, millimetric technical data, and elite educational guides on risk and emotional management. Secure your spot in the free environment before the VIP transition.
By using this site, you agree to our Terms of Use of Use and Privacy Policy
Lithium Americas (TSX, NYSE: LAC) is accelerating spending and construction at its Thacker Pass lithium project in Nevada, US, as the company targets late-2027 completion of what is poised to become one the Western Hemisphere’s largest lithium sources.
The company expects Phase 1 capital spending of $1.3 billion to $1.6 billion this year as detailed engineering nears completion and procurement surpasses 70%, it said amid its first-quarter results. More than 1,300 workers are now on site, with peak construction expected to exceed 2,000.
Lithium Americas has capitalized $1.3 billion in construction and project-related costs so far, including $1.1 billion tied directly to the project’s total estimated capex of $2.93 billion.
The company also said it has begun work on a definitive capital estimate that will account for tariffs, inflation, fuel costs and disruptions linked to Middle East shipping routes.
“At a moment when resilient domestic supply chains are more critical than ever, lithium stands out as a strategic resource underpinning both national security and a reliable energy future,” CEO Jonathan Evans said in the release.
Supply-chain risks
Lithium Americas said more than 75% of structural steel for the project is either in transit or already at site after shipments were rerouted through Saudi Arabia’s Port of Jeddah to avoid disruptions tied to the Strait of Hormuz conflict. Major long-lead equipment including transformers, reactors and steam turbine components is also arriving.
The company estimates tariff exposure for Phase 1 construction at $80 million to $120 million, most of which is expected this year. Construction has also started on a transload terminal near Winnemucca that will support reagent deliveries once the mine enters production.
Strategic push
Thacker Pass’ scale and political backing highlight how aggressively the US is pushing to secure domestic supplies of battery metals as tensions with China intensify.
Once complete, the mine is expected to produce 40,000 tonnes of lithium carbonate annually, enough for roughly 800,000 electric vehicles and well above output from Albemarle’s (NYSE: ALB) Silver Peak mine, currently the only operating lithium brine mine in the US.
The project has drawn strategic backing from General Motors (NYSE: GM), Orion Resource Partners and the US government, which last year took separate 5% stakes in both Lithium Americas and the Thacker Pass project itself. Lithium Americas ended the quarter with about $1.2 billion in cash and restricted cash, including $529 million at the Thacker Pass joint venture level, after receiving another $432-million advance from a Department of Energy loan facility.
Evans said lithium market conditions are improving ahead of the project’s expected startup in late 2027 and ramp-up through 2028.