Construction on track for Q1 completion at Sibanye’s Keliber lithium project in Finland

🎧
Analista ExpertFX

ExpertFX Podcast -
No time to read? Let me read it for you. Press Play!


Ben Graham
 Share

Recommended Posts

  • REDATOR

Sibanye-Stillwater (JSE: SSW, NYSE: SBSW) said on Monday it is on track to complete construction and cold commissioning of its Keliber lithium project in Finland this quarter.

The Keliber lithium project is Europe’s (EU) most advanced integrated lithium project, with planned battery-grade lithium hydroxide monohydrate (LiOH) production of around 15,000 tonnes per annum for over 18 years, Sibanye said. 

As one of the few LiOH refineries outside China, the project has been classified as a strategic project by the EU, aligned with the EU’s strategic initiative for critical minerals, the Critical Raw Materials Act (CRMA).

The total capital investment to complete the project’s construction is estimated to be approximately €783 million, according to the company.

Staged start

Sibanye and its strategic partner in the project, the Finnish Minerals Group, have agreed that a staged start-up of operations is the optimal way forward, given current market conditions.

A staged commissioning of the mine, concentrator and refinery would reduce the project’s ramp-up risk by initially ensuring operational readiness in the mining and concentrating stages, before making a decision on the timing of the commissioning of the refinery, the South African miner said.

Sibanye added that this approach would help maintain project financing flexibility by enabling capital expenditures and refining ramp-up costs to be deferred, based on lithium prices and other market factors.

The Finnish Minerals Group is preparing to participate pro rata to its equity stake in the project (20%) for additional financing required to sustain the project through the ramp-up period.

“The staged ramp-up we have agreed on with our strategic partner ensures that the Keliber lithium project advances responsibly, derisking the commissioning phase to ensure an optimal technical and commercial approach, balancing market realities with stakeholder interests,” Sibanye-Stillwater CEO Richard Stewart said in a news release.

“We have invested significant capital through the price cycle to complete the construction phase of the Keliber lithium project, ensuring this strategic asset is ready to deliver local supply into the EU battery value chain,” Stewart added.

  • Liked! 1
  • Perfect! 1
  • Wow! 1
  • Nova Reação 1
💬 Did you like this content? Your feedback is very important!
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Terminal Visitor
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

 Share

TRADING HUB
● MARKET OPEN
Loading...
RETAILS SENTIMENT
INVERSE
  • Loading...


×
×
  • Create New...

Important Information

By using this site, you agree to our Terms of Use of Use and Privacy Policy

Search In
  • More options...
Find results that contain...
Find results in...

Write what you are looking for and press enter or click the search icon to begin your search

Enjoying ExpertFX? 📈
Your review helps our community grow. Rate the app in seconds.