Barrick warns about âsignificant increasesâ to the budget, timeline for Pakistanâs copper project


Discover exactly where Smart Money is moving capital in real-time. By registering on our platform, you unlock the complete ExpertFX ecosystem: high-precision consensus algorithms, millimetric technical data, and elite educational guides on risk and emotional management. Secure your spot in the free environment before the VIP transition.
By using this site, you agree to our Terms of Use of Use and Privacy Policy
Barrick Mining (NYSE:B)(TSX:ABX) said on Thursday that it anticipates that there could be âsignificant increasesâ to the previously disclosed total estimated capital budget and timeline for its Reko Diq copper project in Pakistan. Â
On March 26, Barrick said it will slow its development of the Reko Diq deposit and extend the projectâs review period, citing security concerns in the Middle East.Â
Reko Diq, one of the worldâs largest undeveloped deposits of the metal, is in the remote, insurgency-hit western province of Balochistan and held in an equal partnership between the company and the Pakistani authorities.Â
The previously disclosed total estimated capital cost of Phase 1 was between $5.6 billion and $6.0 billion (100% basis, exclusive of capitalization of financing costs) and of Phase 2 was between $3.3 billion and $3.6 billion (100% basis, exclusive of capitalization of financing costs), with first production targeted by the end of 2028.Â
Barrick, which has been developing the project in partnership with the governments of Pakistan and Balochistan for years, initially planned for the project to come online in 2028, subject to financing.  Â
Once operational, the mine is forecast to generate over $70 billion in free cash flow and $90 billion in operating cash flow over a 37-year lifespan.Â