Discover exactly where Smart Money is moving capital in real-time. By registering on our platform, you unlock the complete ExpertFX ecosystem: high-precision consensus algorithms, millimetric technical data, and elite educational guides on risk and emotional management. Secure your spot in the free environment before the VIP transition.
By using this site, you agree to our Terms of Use of Use and Privacy Policy
Seabridge Goldâs (TSX: SEA; NYSE: SA) push for permits to dig tunnels at its giant KSM project is being delayed by British Columbia until the minerâs court fight with neighbour Tudor Gold (TSXV: TUD) is resolved.
The twin tunnels are a core link in the $6.4 billion capex KSM project, carrying ore from mining in the Mitchell Valley to processing facilities in the Treaty Valley. Part of the route crosses Tudor claims and Seabridge already holds some permits. But the province wonât rule on the rest of them while Tudor challenges Seabridge in provincial court.
âWe have always been clear that if Tudor has an approved and permitted mine plan for its Goldstorm project, then we are willing to sit down and find an amicable solution to the Mitchell Treaty tunnels (MTT) issue,â CEO Rudi Fronk said Friday in a news release. âHowever, agreeing to move the MTT route before Tudor has a defined project makes no sense.â
The delay comes after Seabridgeâs KSM had cleared other major hurdles. These include the mid-2024 âsubstantially startedâ designation from the BC government which cemented KSMâs Environmental Assessment Act permit for the life of the project; the narrowing of its search for a development partner to one company; and last monthâs small victory in court when Tudor dropped one of its appeals.
Several fights
The details of the court fight concern whether Seabridgeâs conditional mineral reserve for KSM, first granted in 2012, binds claims that predate it, and whether the province has authority to grant tunnel-related rights across them. The ministry has on several occasions confirmed in writing that the reserve applies to Tudorâs ground, Seabridge said.
Tudor has argued for months that the tunnel route, as planned, would cut through the Goldstorm deposit and the nearby Perfectstorm target on its Treaty Creek project. In October, it proposed a northern reroute that it said could let both projects advance. In December the company reiterated that negotiation with Seabridge and the province offered the best path, even as it said it was pressing ahead with court proceedings to preserve its rights.
Seabridge said it still has no plans to begin tunnel construction before it completes a final feasibility study and announces a project partner.
Tudor started compiling a preliminary economic assessment due by the third quarter for a 10,000-tonne-per-day underground mine at Goldstorm after updating the resource in January. Seabridge, meanwhile, said last month that securing a KSM partner is its top goal this year and updated KSMâs resources days later.
Seabridgeâs Toronto-listed shares fell 4.3% on Friday-afternoon trades to C$42.89 per share, giving it a market capitalization of C$4.6 billion ($3.3 billion). Tudor shares were trading down 1% at C$0.99 by midday, giving it a market cap of C$404 million ($292 million).
Big resources
The size of the resources helps explain why neither side has backed down. Tudorâs January resource estimate outlined 912.3 million indicated tonnes grading 0.85 gram gold, 5.07 grams silver and 0.15% copper for 24.9 million oz. gold, 148.7 million oz. silver and 3.1 billion lb. copper.
Inferred resources add 86.1 million tonnes grading 1.43 grams gold, 5.22 grams silver and 0.17% copper for 4 million oz. gold, 18.6 million oz. silver and 327.7 million lb. copper.
Seabridgeâs resource update last month showed higher metal price assumptions lifted measured and indicated resources by 6.8 million oz. gold and inferred resources by 12.9 million oz. without changing the underlying geology model. The project carries proven and probable reserves of 2.3 billion tonnes grading 0.64 gram gold, 0.14% copper and 2.2 grams silver for 47.3 million oz. gold, 7.3 billion lb. copper and 160 million oz. silver. The same study outlined a 33-year mine life and average yearly output of 1.03 million oz. gold and 178 million lb. copper.