Giyani Metals' study shows a leaner and more primitive manganese project in Botswana

Voice

ExpertFX Podcast - No time to read? Let me read it for you. Press Play!

A feasibility study for Giyani Metals’ (TSXV: EMM) K. Hill open pit manganese project in Botswana outlines a much costlier operation and with lower value than in a previous economic study, though it’s now backed with proven reserves.

At an 8% discount rate, the study gives K. Hill a post-tax net present value of $481.5 million, half of the value estimated in the 2023 preliminary economic assessment (PEA), Giyani reported Thursday.

Initial capital costs rose 88% to $535 million, the internal rate of return fell by 9 percentage points to 20% and manganese production is down 57% to 1.5 million tonnes, Giyani said. Mine life is also cut by more than half to 25 years. K. Hill is about 60 km southwest of the capital Gaborone.

“These results
 endorse K. Hill as a unique, mine to-market battery-grade supplier of manganese to meet growing Western demand, and provide a solid foundation for further optimization and continued development of the project,” Giyani’s interim executive chair Nigel Robinson said in a release.

“Building on the successful production of both high-purity manganese oxide (HPMO) and high-purity manganese sulphate monohydrate (HPMSM) from our demonstration plant in Johannesburg, we are now well-positioned to meet the evolving requirements of the battery and energy storage markets.”

Small supply chain

Manganese, a key ingredient in steelmaking and increasingly valued in the form of HPMSM for electric vehicle batteries, is mined mainly in countries such as South Africa, Australia and Gabon, while China dominates battery-grade manganese processing. Few Western countries produce manganese in significant quantities outside Australia and, to a lesser extent, Brazil.

Giyani shares gained 5% on Thursday morning in Toronto, for a market capitalization of C$33.1 million ($24 million).

Adds proven reserves

The feasibility study upgraded the deposit over the 2023 PEA. It estimates that K. Hill hosts proven and probable reserves of 5.3 million tonnes grading 12% manganese oxide for about 642,000 tonnes of contained metal.

Construction of the mine at K. Hill could start in early 2027, with commissioning in late 2028 and process plant ramp-up in 2029, the study shows.

  PREMIUM - EXPERTFX SCHOOL
  ExpertFX School: Leading the Gold market since 2017. Secure your spot in the Elite.
ACCESS PREMIUM DASHBOARD
Latest comments

Join the conversation

You can article now and register later. If you have an account, sign in now to article with your account.
Note: Your article will require moderator approval before it will be visible.

Terminal Visitor
What is your take on this move?

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...


  • ACCESS A MARKET

    Discover exactly where Smart Money is moving capital in real-time. By registering on our platform, you unlock the complete ExpertFX ecosystem: high-precision consensus algorithms, millimetric technical data, and elite educational guides on risk and emotional management. Secure your spot in the free environment before the VIP transition.

Live Global Sessions
Real-time NYSE Data Feed
Enjoying ExpertFX? 📈
Your review helps our community grow. Rate the app in seconds.
★ ★ ★ ★ ★

Important Information

By using this site, you agree to our Terms of Use of Use and Privacy Policy

×
×
  • Create New...