Ivanhoe slashes 2025 copper guidance by 28% following DRC mine restart


Redator

Posts Recomendados

255292_36a496e1c4582945_005full-1024x500
Kakula mine looking north, with the Phase 1 and 2 concentrators in the background. Credit: Ivanhoe Mines

Ivanhoe Mines (TSX: IVN) says it has restarted the western portion of the Kakula copper mine in the Democratic Republic of the Congo following its temporary suspension nearly a month ago.

The underground mine, part of the company’s larger Kamoa-Kakula copper complex in the DRC, was forced to shut down on May 18 due to severe flooding that resulted from seismic activity in the region. The complex is Africa’s largest copper-producing operation, with majority ownership split between Ivanhoe and China’s Zijin Mining at 39.6% each, while the DRC government holds a 20% stake.

Despite conflicted reports over the potential damage by Ivanhoe and its joint venture partner Zijin, industry analysts have said the mine should be able to resume once the necessary dewatering and remediation efforts are completed.

On Wednesday, Ivanhoe confirmed that the western section of the Kakula returned to operations “in a safe and conservative manner” on June 7 after the flooding had stabilized following the installation of additional water pumping capacity.

Mining activities in the eastern side are also expected to start imminently, focused solely on developing access drives to a new mining area east of the existing mine workings, it added.

“We are thankful and deeply appreciate our team’s swift response to stabilize underground water levels in the Kakula mine and resume mining on the western side,” executive co-chair Robert Friedland commented.

“The team has quickly secured the critical equipment needed to safely dewater the entirety of the mine, while preparing to access a new high-grade mining area in the east.”

Revised guidance

With the mining restart, Ivanhoe has presented a new 2025 production guidance for the Kamoa-Kakula complex: between 370,000 and 420,000 tonnes of copper in concentrates.

This forecast, based on the midpoint of its guidance range, represents a 28% decrease over the company’s prior guidance (between 520,000 and 580,000 tonnes) set in January.

With the downward guidance, shares of Ivanhoe fell 5.9% at C$10.86 apiece at Wednesday’s close, taking its market capitalization to C$14.6 billion ($10.7 billion).

According to Ivanhoe, the guidance was revised down after taking into the probable effect of recent seismic activity and associated interruptions in operations at the Kakula mine. It also highlighted several risk factors that were taken into consideration, such as further seismic activity and infrastructure breakdown.

In addition, management has also withdrawn its 2026 target of approximately 600,000 tonnes of copper production, pending further review.

“While it’s still too early to outline our detailed plans for 2026 and 2027, the future remains bright across the Kamoa-Kakula copper complex,” Friedland reiterated in the press release.

As previously disclosed, the Phase 1 and 2 concentrators at Kakula are still operating at approximately 50% of their combined operating capacity, processing ore from surface stockpiles. The processing rate of the concentrators is expected to ramp up throughout the remainder of 2025, as mining from the western side of the mine increases, Ivanhoe said.

Meanwhile, mining operations at the Kamoa underground mine, as well as ore processing at the adjacent Phase 3 concentrator, continue to outperform, it added.

With the necessary copper concentrate expected to be available, the on-site smelter is anticipated to start up in September, with first production expected in October 2025.

Link para o comentário
Compartilhar em outros sites

Participe da Conversa

Você pode postar agora e se cadastrar mais tarde. Cadastre-se Agora para publicar com Sua Conta.
Observação: sua postagem exigirá aprovação do moderador antes de ficar visível.

Visitante
Responder

×   Você colou conteúdo com formatação.   Remover formatação

  Apenas 75 emoticons são permitidos.

×   Seu link foi incorporado automaticamente.   Exibir como um link em vez disso

×   Seu conteúdo anterior foi restaurado.   Limpar Editor

×   Você não pode colar imagens diretamente. Carregar ou inserir imagens do URL.

×
×
  • Criar Novo...

Informação Importante

Ao utilizar este site, você concorda com nossos Termos de Uso de Uso e Política de Privacidade

Pesquisar em
  • Mais opções...
Encontrar resultados que...
Encontrar resultados em...

Write what you are looking for and press enter or click the search icon to begin your search