Lithium Ionic boosts projected returns for Brazil project


Redator

Posts Recomendados

  • REDATOR

Lithium Ionic (TSXV: LTH) said a definitive feasibility study for its Bandeira project in eastern Brazil shows higher returns, lower capital costs and a longer mine life than prior calculations.

Thanks to increased reserves and an optimized mine design, Bandeira is now projected to deliver a post-tax net present value of $1.45 billion instead of the $1.31 billion estimated by a May 2024 study, Lithium Ionic said Wednesday in a statement. The project’s internal rate of return climbs to 61% from 40% while the payback period shrinks to 2.2 years from 3.4 years.

News of the improved economics comes about four months after Lithium Ionic lifted the project’s contained resources by about one-third over the 2024 study. Located in Minas Gerais state, Bandeira sits about 1,000 km north of Rio de Janeiro. Production is expected to start in the second half of next year, according to a presentation posted on the company’s website.

“What was already a robust project is now even stronger – delivering a longer mine life, lower capital requirements and significantly improved project economics,” CEO Blake Hylands said in a statement. “These results reinforce Bandeira’s position as one of the most competitive hard-rock lithium projects globally.”

Lithium Ionic shares advanced 3.8% to C$0.82 Wednesday morning in Toronto, giving the company a market value of about C$130 million. The stock has traded between C$0.50 and C$1.15 in the past year.

First quartile

Capital expenditures – including contingency – are now estimated at $191 million, 28% less than the $266 million calculated earlier. Operating expenses are pegged at $378 per tonne of spodumene concentrate, which the company says would put the project in the first quartile of global lithium production costs.

Bandeira is projected to operate for 18.5 years, up from 14 years in the prior study. Annual spodumene concentrate output should average 177,000 tonnes over the mine’s life, the company says.

Measured and indicated resources now total 27.27 million tonnes grading 1.34% lithium oxide (Li₂O) for 901,059 tonnes of lithium carbonate equivalent (LCE), compared with the 696,520 contained tonnes in last year’s study, the company said May 6. Inferred resources for the project logged a slight 1.9% increase to 18.55 million tonnes at 1.34% Li₂O, or 615,432 contained tonnes of LCE.

The project claims sit across 1.6 sq. km, representing about 1% of the company’s 141.8-sq.-km land package in Brazil’s “Lithium Valley.” The area is also home to another Lithium Ionic project, Salinas, about 120 km north of Bandeira.

Link para o comentário
Compartilhar em outros sites

Participe da Conversa

Você pode postar agora e se cadastrar mais tarde. Cadastre-se Agora para publicar com Sua Conta.
Observação: sua postagem exigirá aprovação do moderador antes de ficar visível.

Visitante
Responder

×   Você colou conteúdo com formatação.   Remover formatação

  Apenas 75 emoticons são permitidos.

×   Seu link foi incorporado automaticamente.   Exibir como um link em vez disso

×   Seu conteúdo anterior foi restaurado.   Limpar Editor

×   Você não pode colar imagens diretamente. Carregar ou inserir imagens do URL.

  • 📊 Trading Hub

    Resumo rápido de mercados em tempo real
    Carregando...
  • 📟 Forex Terminal

    • Carregando dados do mercado...
    🔎 Ver dados completos
  • 📅 Próximo Evento no Radar

    Carregando...




    ×
    ×
    • Criar Novo...

    Informação Importante

    Ao utilizar este site, você concorda com nossos Termos de Uso de Uso e Política de Privacidade

    Pesquisar em
    • Mais opções...
    Encontrar resultados que...
    Encontrar resultados em...

    Write what you are looking for and press enter or click the search icon to begin your search